PROJECT CONCERNS

This project required a large reserve of resin on the pump truck due to the scale of the bridge. E-Chem provided enough material to complete over 2,000 SY in a single shift without reloading. The contractor was able to install an average of 10,000 sf/hr. with the pump shown and a crew of 6 installers. This bridge was completed in two single shift days allowing the contractor to complete this project ahead of schedule.

EPX-50 HIGHLIGHTS


  • 100% SOLIDS
  • Low Odor
  • WORKER FRIENDLY
  • EASY 1:1 RATIO
  • LOW MODULUS
  • RAPID TURNAROUND
  • WATERPROOF
  • MOISTURE INSENSITIVE
  • SELF-PRIMING
EPX50-Overlay & Lake County Phonolite

PROJECT RESULTS

  • Bridge installation completed in two shifts, cleanup completed prior to dark.
  • Increased project profitability due to solutions oriented approach.
  • Reduced worker exposure to hazardous traffic conditions.
  • High volume, high accuracy epoxy placement.